Pool Project Update - 2016 Grand Opening
Posted on Oct 24th, 2014

Thank you to everyone who supported the new pool project!  We successfully received the required number of signatures to move forward.  The project will begin at the close of the 2015 summer season and the new pool project will be ready for the 2016 swimming season.
 
The original plan was to have the new pool completed for the 2015 opening, but with long processing times for loans and permit approvals, it was not possible to open on time for the 2015 season.  The adjusted time frame will allow the new pool and surrounding area to be open on time for the 2016 season.
 
The immediate next steps are as follows:
  • Finalize the loan commitment and submit a down payment
  • Receive proposed plans from contractors and provide Board approval
  • Contractors to file for mandatory permits
  • All final plans to be submitted to the state for approval (could take 3-4 months to approve)
  • Demolition of the existing pool after state approval
  • Begin installation of the new pool and surrounding area.
Please contact a Board member with any additional questions.  Thank you again for your support!